據(jù)Oil & Gas Journal網(wǎng)站6月29日?qǐng)?bào)道 波蘭天然氣輸送系統(tǒng)運(yùn)營(yíng)商Gaz-System SA的全資子公司Polskie LN、Szczecin以及?winouj?cie海港管理局已與Porr SA和TGE Gas Engineering GMBH簽訂協(xié)議,將Lech Kaczyński液化天然氣終端產(chǎn)能擴(kuò)建至830萬(wàn)噸/年。協(xié)議包括系統(tǒng)設(shè)計(jì)、許可、施工和調(diào)試,兩家公司預(yù)計(jì)在2023年底前完成擴(kuò)建。
Polskie LNG將監(jiān)督第三個(gè)16萬(wàn)立方米液化天然氣儲(chǔ)罐和第二個(gè)泊位的建造。Szczecin和?winouj?cie海港管理局將負(fù)責(zé)泊位的水工部分、相關(guān)傳輸管架的水工基礎(chǔ)設(shè)施以及完整的系泊基礎(chǔ)設(shè)施。簽署的協(xié)議總價(jià)值約為19億茲羅提(4.8億美元)。擴(kuò)建還將包括配備鐵路轉(zhuǎn)運(yùn)能力。
2020年5月29日,Polskie LNG與波蘭國(guó)家石油天然氣公司(PGNiG)簽署了與擴(kuò)建相關(guān)的天然氣供應(yīng)協(xié)議。
Gaz-System還開發(fā)了波羅的海管道項(xiàng)目,將挪威的天然氣輸送至波蘭和丹麥(2022年完工);南北天然氣走廊,連接波蘭和克羅地亞的液化天然氣終端(2022年);以及連接兩國(guó)輸氣系統(tǒng)的波蘭-立陶宛天然氣互聯(lián)項(xiàng)目(2021年)。
吳恒磊 編譯自 Oil & Gas Journal
原文如下:
Polskie LNG signs terminal expansion agreements
Polish gas transmission system operator Gaz-System SA’s wholly-owned affiliate Polskie LNG and Szczecin and ?winouj?cie Seaport Authority have signed agreements with Porr SA and TGE Gas Engineering GMBH for a 3.3-million tonnne/year (tpy) expansion of the Lech Kaczyński LNG terminal, to 8.3 million tpy. The agreements cover system design, permitting, construction, and commissioning. The companies expect to complete the expansion by end-2023.
Polskie LNG will oversee construction of a third 160,000-cu m LNG tank and second berth. Szczecin and ?winouj?cie Seaport Authority will be responsible for the hydrotechnical part of the berth, hydrotechnical infrastructure for the associated transmission pipe rack, and complete mooring infrastructure. The value of the signed agreements totals roughly PLN 1.9 billion ($480 million). The expansion will also include installation of rail transshipment capability.
On May 29, 2020, Polskie LNG and Polish-state oil and gas company PGNiG signed a gas supply agreement for volumes associated with the expansion.
Gaz-System is also developing the Baltic Pipe project, bringing gas from Norway to Poland and Denmark (completion 2022); the North-South Gas Corridor, linking LNG terminals in Poland and Croatia (2022); and Gas Interconnection Poland-Lithuania, connecting the two countries transmission systems (2021).